Review Agenda Item
Meeting Date: 2/12/2020 - 3:00 PM
Category: Consent Calendar
Type: Action
Subject: 12.23 BUILDING AND GROUNDS: Notice of Completion for the Paloma Valley High School Classroom Addition and Stadium Improvements Project - Various Categories and the Perris High School Phase 2B and PACE Project (no fiscal impact)
Strategic Plan:
Enclosure
File Attachment:
NOC Letter (KAR,JPI,Ryan).pdf
RND Notice of Completion - Phase 2 AG.pdf
RND Notice of Completion - Phase 2B.pdf
Summary: The District recommends that a Notice of Completion be filed for the following contractors:

Paloma Valley High School Classroom Addition and Stadium Improvements Project:
- Category 01 - Concrete, KAR Construction, Inc.
- Category 18 - Plumbing, JPI Development, Inc.
- Category 19 - Electrical, Ryan Electric

Perris High School Phase 2B and PACE Project:
- Category 05B - RND Contractors, Inc.
Funding: No fiscal impact.
Recommendation: It is recommended that the Board of Trustees approve the Notice of Completion for the Paloma Valley High School Classroom Addition and Stadium Improvements Project - Various Categories and the Perris High School Phase 2B and PACE Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member Dr. Jose Luis Araux Moved, Member Edward Garcia, Jr. seconded to approve the Original motion 'It is recommended that the Board of Trustees approve the Notice of Completion for the Paloma Valley High School Classroom Addition and Stadium Improvements Project - Various Categories and the Perris High School Phase 2B and PACE Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Dr. Jose Luis Araux     Yes
Anthony T. Stafford, Sr.     Yes
David Nelissen     Yes
Dr. Randall Freeman     Yes
Edward Garcia, Jr.     Yes