Review Agenda Item
Meeting Date: 5/15/2019 - 3:45 PM
Category: Action Items
Type: Action
Subject: 14.9 BUILDING AND GROUNDS: Inspector of Record Agreement With Construction Quality Assurance Group, LLC for the California Military Institute Gym and Parking/Circulation Project (funded through Various Facilities Funds estimated at $375,384, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
CQAG - IOR Services CMI Gym and Parking_Circulation Project.pdf
PROPOSAL_PUHSD_CALIFORNIA MILITARY INST_GYMNASIUM PROJECT_04-117653_2.0.pdf
Summary: The District would like to extend the contract for the Division of State Architects (DSA) Inspector of Record (IOR) services for the CMI, Gym and Parking/Circulation Project to CQAG. The IOR verifies that construction of a project follows and adheres to the plans and specifications as approved by the DSA office. The duties of the IOR are defined in the California Code of Regulations, Title 24, Part 1, Section 4-342. In addition, the IOR works with the District to mitigate the effects of construction activities and operations on a school site and to make sure all applicable safety standards are being followed. The DSA IOR services are provided through project completion and will be billed at an hourly rate of $103. The hourly rate will increase to $105 on January 2020 as per the CQAG Proposal. The estimated project cost is $375,384.
Funding: The cost for this item is included in the 2018-19 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees approve the Inspector of Record Agreement with Construction Quality Assurance Group, LLC for the California Military Institute Gym and Parking/Circulation Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member David Nelissen Moved, Member Anthony T. Stafford, Sr. seconded to approve the Original motion 'It is recommended that the Board of Trustees approve the Inspector of Record Agreement with Construction Quality Assurance Group, LLC for the California Military Institute Gym and Parking/Circulation Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Dr. Randall Freeman     Yes
Anthony T. Stafford, Sr.     Yes
Edward Garcia, Jr.     Yes
David Nelissen     Yes
Dr. Jose Luis Araux     Yes