Review Agenda Item
Meeting Date: 4/15/2020 - 3:30 PM
Category: Consent Calendar
Type: Action
Subject: 11.9 BUILDING & GROUNDS: Ratification of Proposal from Inland Inspections and Consulting for Division of State Architects Inspector of Record Services for the Perris High School Increment 1 Project (funded through Various Facilities Funds at an estimated cost of $39,000, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
Perris UHSD Perris HS Increment 1.pdf
Summary: The District entered into an Agreement for Division of State Architects (DSA) Inspector of Record (IOR) Services for the Perris High School Increment 1 Project with Inland Inspections and Consulting. The IOR verifies that the construction of a project follows and adheres to the plans and specifications as approved by the DSA office. The duties of the IOR are defined in the California Code of Regulations, Title 24, Part 1, Section 4-342. In addition, the IOR works with the District to mitigate the effects of construction activities and operations on a school site and to make sure all applicable safety standards are being followed. The DSA IOR services are provided through project completion and will be billed at an hourly rate of $97.50 with an estimated project cost of $39,000.

The timing of this component of the project was moved up as a result of ordered school closures and is therefore being brought forward to the Board as a ratification. Ratification is permitted for Board approved facilities projects pursuant to Purchasing Policy.
Funding: The cost for this item is included in the 2019-20 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees ratify the Proposal from Inland Inspections and Consulting for Division of State Architects Inspector of Record Services for the Perris High School Increment 1 Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Dawn Bray - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member David Nelissen Moved, Member Edward Garcia, Jr. seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify the Proposal from Inland Inspections and Consulting for Division of State Architects Inspector of Record Services for the Perris High School Increment 1 Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Dr. Randall Freeman     Yes
Edward Garcia, Jr.     Yes
Anthony T. Stafford, Sr.     Yes
David Nelissen     Yes
Dr. Jose Luis Araux     Yes